FAR proposal narrows deficiency to material-term nonconformance
The test flips from whether a non-conformance was material to whether the underlying requirement itself was material.
TL;DR
The FAR Council's proposed Part 15 rewrite would redefine "deficiency" as any part of a proposal that doesn't conform to a material term of the RFP, meaning a term affecting price, quantity, quality, delivery, or a prerequisite due at submission. Under the current definition, a combination of significant weaknesses could also establish a deficiency; that path disappears. For offerors, Covington notes the change narrows and clarifies when an agency can declare a proposal ineligible, and gives a protester a cleaner argument that an awardee should have been found deficient.
The move is subtle but the inversion matters. Under FAR 15.001 today, a deficiency is either a "material failure . . . to meet a Government requirement" or "a combination of significant weaknesses" that pushes risk of unsuccessful performance to an unacceptable level. The operative question was whether the non-conformance was material. The proposed rule reverses the lens: a deficiency becomes "any part of a proposal that does not conform to a material term of an RFP," and the question becomes whether the requirement itself was material.
That's the clarification Covington flags as helpful. The old language seemed to sweep in all requirements and then ask how serious the departure was. The new language applies only to material terms, and any deviation from one counts. That more clearly draws the line both for agencies assigning a deficiency and for a protester arguing the awardee should have been found deficient and unawardable.
The second change is the sharper one. A combination of significant weaknesses could no longer be treated as a deficiency, so a risky approach to meeting future requirements can't by itself render an offeror ineligible. Covington's read is that an agency probably isn't any more likely to award to such an offeror anyway; it can still cite the risky approach as grounds for low technical ratings and as a discriminator in a best-value analysis. But the offeror in that position gets an easier protest posture, because it no longer has to overcome a finding of ineligibility.
One limit worth keeping straight: the proposed rule doesn't take future requirements off the table. An agency can still assign a deficiency to a proposal that deviates from a future requirement, so long as that requirement is material. The net effect is a definition that is narrower in what it sweeps in, but clearer in what it actually catches. Whether the FAR Council finalizes this framing, and how pending protests under the old definition get handled in the meantime, is the open question.
Published ·Deep Fathom